STRATEGY CCUS | STRATEGIC PLANNING OF REGIONS AND TERRITORIES IN EUROPE FOR LOW-CARBON ENERGY AND INDUSTRY THROUGH CCUS

Summary
The STRATEGY CCUS project aims to elaborate strategic plans for CCUS development in Southern and Eastern Europe at short term (up to 3 years), medium term (3-10 years) and long term (more than 10 years). Specific objectives are to develop:
•Local CCUS development plans, with local business models, within promising start‐up regions;
•Connection plans with transport corridors between local CCUS clusters, and with the North Sea infrastructure, in order to improve performance and reduce costs, thus contributing to build a Europe-wide CCUS infrastructure.
As recommended by the SET Plan Action 9, the STRATEGY CCUS project will study options for CCUS clusters in Eastern and Southern Europe, as at present the CCUS clusters being progressed are concentrated in Western Europe around the North Sea. Therefore, the project is timely for the strategic planning for CCUS development in the whole of Europe.
Strategic planning will consider 8 promising regions, within 7 countries (ES, FR, GR, HR, PO, PT, RO) representing 45% of the European CO2 emissions from the industry and energy sectors. These regions satisfy CCUS relevant criteria: presence of an industrial cluster, possibilities for CO2 storage and/or utilization, potential for coupling with hydrogen production and use, existing studies, and political will.
The methodology starts with a detailed mapping of CCUS technical potential of the regions together with a comprehensive mapping of local stakeholders and a process for their engagement. This will pave the ground for CCUS deployment scenarios including assessment of 'bankable' storage capacity, economic and environmental evaluation.
The project strength relies on of a highly skilled consortium with experience on the whole CCUS chain as well as key transverse skills. CCUS development plans will be elaborated in close cooperation with stakeholders, through the Regional Stakeholder Committees and the Industry Club, to ensure plans can be implemented, i.e. socially acceptable.
Unfold all
/
Fold all
More information & hyperlinks
Web resources: https://cordis.europa.eu/project/id/837754
Start date: 01-05-2019
End date: 31-07-2022
Total budget - Public funding: 3 069 473,00 Euro - 2 959 533,00 Euro
Cordis data

Original description

The STRATEGY CCUS project aims to elaborate strategic plans for CCUS development in Southern and Eastern Europe at short term (up to 3 years), medium term (3-10 years) and long term (more than 10 years). Specific objectives are to develop:
•Local CCUS development plans, with local business models, within promising start‐up regions;
•Connection plans with transport corridors between local CCUS clusters, and with the North Sea infrastructure, in order to improve performance and reduce costs, thus contributing to build a Europe-wide CCUS infrastructure.
As recommended by the SET Plan Action 9, the STRATEGY CCUS project will study options for CCUS clusters in Eastern and Southern Europe, as at present the CCUS clusters being progressed are concentrated in Western Europe around the North Sea. Therefore, the project is timely for the strategic planning for CCUS development in the whole of Europe.
Strategic planning will consider 8 promising regions, within 7 countries (ES, FR, GR, HR, PO, PT, RO) representing 45% of the European CO2 emissions from the industry and energy sectors. These regions satisfy CCUS relevant criteria: presence of an industrial cluster, possibilities for CO2 storage and/or utilization, potential for coupling with hydrogen production and use, existing studies, and political will.
The methodology starts with a detailed mapping of CCUS technical potential of the regions together with a comprehensive mapping of local stakeholders and a process for their engagement. This will pave the ground for CCUS deployment scenarios including assessment of 'bankable' storage capacity, economic and environmental evaluation.
The project strength relies on of a highly skilled consortium with experience on the whole CCUS chain as well as key transverse skills. CCUS development plans will be elaborated in close cooperation with stakeholders, through the Regional Stakeholder Committees and the Industry Club, to ensure plans can be implemented, i.e. socially acceptable.

Status

CLOSED

Call topic

LC-SC3-NZE-3-2018

Update Date

26-10-2022
Images
No images available.
Geographical location(s)
Structured mapping
Unfold all
/
Fold all
Horizon 2020
H2020-EU.3. SOCIETAL CHALLENGES
H2020-EU.3.3. SOCIETAL CHALLENGES - Secure, clean and efficient energy
H2020-EU.3.3.2. Low-cost, low-carbon energy supply
H2020-EU.3.3.2.0. Cross-cutting call topics
H2020-LC-SC3-2018-NZE-CC
LC-SC3-NZE-3-2018 Strategic planning for CCUS development