Eastern Lights | Development of CO2 transport and storage demo project in Eastern Europe - Eastern Lights

Summary
Eastern Lights (EL) is the de-risking first step to develop a large-scale CCUS cluster in Eastern Europe. The Holcim Bulgaria plant will be the heart and engine of the cluster development starting with CO2 transport and storage (T&S) demonstration in North West Bulgaria. EL will de-risk the CO2 transport and storage by eliminating the main uncertainties of T&S by industrial demonstration, in-depth studies and stakeholder engagement. By constructing and testing a km long transport pipeline fully integrated into the commercial operating CO2 storage, the key process parameters and technical aspects for a full-scale CCUS complex will be validated. The critical risks of the T&S part will be eliminated by an industrial demonstration and comprehensive set of studies leading to permitting.

To minimize the risks, saline aquifers from North West Bulgaria will be used for safe and large capacity CO2 storage close to a major CO2 source and Bulgarian pipeline corridors. Extensive geological, geophysical and testing work will be done to address critical issues as induced seismicity and safe injection over time. By actually constructing a short pipeline, specific issues like land-owner allowances will be addressed and the transport will be made ready for permitting and execution for the entire corridor cross-border cluster connecting members to the CO2 sink. Intensive communication, stakeholder consultation, cluster development and permit preparations will complete the Eastern Lights scope. As such, Eastern Lights shall unlock the CCUS potential in Eastern Europe, Bulgaria in particular and potentially Romania, therewith contributing to the Fit for 55 targets. Demonstrating an economically feasible decarbonizing track for the (cement) industry in Bulgaria, will secure jobs and economic activity in this field. Strong cross-border ties will be demonstrated by using CO2 from Tupras in Turkey (Mof4Air), and more generally contributing the EU goal to reach climate targets.
Unfold all
/
Fold all
More information & hyperlinks
Web resources: https://cordis.europa.eu/project/id/101136122
Start date: 01-09-2024
End date: 31-08-2028
Total budget - Public funding: 24 215 648,53 Euro - 19 122 237,00 Euro
Cordis data

Original description

Eastern Lights (EL) is the de-risking first step to develop a large-scale CCUS cluster in Eastern Europe. The Holcim Bulgaria plant will be the heart and engine of the cluster development starting with CO2 transport and storage (T&S) demonstration in North West Bulgaria. EL will de-risk the CO2 transport and storage by eliminating the main uncertainties of T&S by industrial demonstration, in-depth studies and stakeholder engagement. By constructing and testing a km long transport pipeline fully integrated into the commercial operating CO2 storage, the key process parameters and technical aspects for a full-scale CCUS complex will be validated. The critical risks of the T&S part will be eliminated by an industrial demonstration and comprehensive set of studies leading to permitting.

To minimize the risks, saline aquifers from North West Bulgaria will be used for safe and large capacity CO2 storage close to a major CO2 source and Bulgarian pipeline corridors. Extensive geological, geophysical and testing work will be done to address critical issues as induced seismicity and safe injection over time. By actually constructing a short pipeline, specific issues like land-owner allowances will be addressed and the transport will be made ready for permitting and execution for the entire corridor cross-border cluster connecting members to the CO2 sink. Intensive communication, stakeholder consultation, cluster development and permit preparations will complete the Eastern Lights scope. As such, Eastern Lights shall unlock the CCUS potential in Eastern Europe, Bulgaria in particular and potentially Romania, therewith contributing to the Fit for 55 targets. Demonstrating an economically feasible decarbonizing track for the (cement) industry in Bulgaria, will secure jobs and economic activity in this field. Strong cross-border ties will be demonstrated by using CO2 from Tupras in Turkey (Mof4Air), and more generally contributing the EU goal to reach climate targets.

Status

SIGNED

Call topic

HORIZON-CL5-2023-D3-01-17

Update Date

03-10-2024
Images
No images available.
Geographical location(s)
Structured mapping
Unfold all
/
Fold all
Horizon Europe
HORIZON.2 Global Challenges and European Industrial Competitiveness
HORIZON.2.5 Climate, Energy and Mobility
HORIZON.2.5.2 Energy Supply
HORIZON-CL5-2023-D3-01
HORIZON-CL5-2023-D3-01-17 Development of CO2 transport and storage demo projects