Site ready

Summary
VK will be responsible for the preparation of the site in Raggovidda. The site will necessarily be located in an area hardly accessible in wintertime, and major construction works will need to be scheduled for summer; VK will build a hall to house the full system, so that work may proceed also in winter. VK will also procure all necessary legal authorisations for the site, and provide suitable heating, internet connection, water supply (extending a previously dug one), and electrical connections to both grid and wind farm. HYG and KES will train VK’s personnel in basic maintenance, safety procedures and general principles of their plant, so that they may promptly intervene in case of minor issues requiring manual intervention on the plant.