This deliverable will comprise the design principles and the ICT architecture of the Integrated controler. Moreover, the study will cover the design and selection of the hardware that will make up the integrated controller of the PV generation, storage systems and grid connection.
First amendment: Validation testing were planned to be performed during September 2020 at CENER's microgrid, but they were not possible to start before mid-November 2020 due to technical problems that raised during the regular maintenance activities. Therefore, an extension of the duration of this task until the end of February 2021 will be requested, and included in the 1st Contract Amendment, in order to complete it satisfactorily.